Benzene

Coire Glas: grid connection queue

Coire Glas GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 1,296 MW is waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.

1project in the queue
1,296 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Coire Glas Pumped StorageCOIRE GLAS HYDRO PUMPED STORAGE LIMITEDHydro, pumped storage and tidal1,29631 Oct 2029Medium31 Oct 2029Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Glen Laogh PrimarySSEN Distribution5.6 km0 MW0.1 MW
Invergarry PrimarySSEN Distribution7.1 km0 MW0.9 MW
Bunarkaig PrimarySSEN Distribution11.1 km0.2 MW0 MW
Aberchalder PrimarySSEN Distribution11.8 km0 MW0.1 MW
Quoich GSPSSEN Distribution15.0 km
Ceannacroc GSPSSEN Distribution15.1 km

Thinking of connecting near Coire Glas?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points