Fort Augustus 400kV: grid connection queue
Fort Augustus 400kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fort Augustus BESS | FIELD DEVCO LTD | Battery storage | 200 | 31 Oct 2035 | Low | 31 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Glendoe Primary | SSEN Distribution | 0.8 km | 0 MW | 0.7 MW |
| Bunoich Primary | SSEN Distribution | 1.8 km | 0 MW | 1.8 MW |
| Fort Augustus GSP | SSEN Distribution | 3.8 km | ||
| Aberchalder Primary | SSEN Distribution | 7.9 km | 0 MW | 0.1 MW |
| Wester Drummond Primary | SSEN Distribution | 8.4 km | 0 MW | 0.1 MW |
| Ardochy Primary | SSEN Distribution | 9.0 km | 0 MW | 0.1 MW |
Thinking of connecting near Fort Augustus 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Fort Augustus 2 400kV: 115 MW waiting
- FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION: 50 MW waiting
- Loch Nan Eun 275/18kV: 900 MW waiting
- Cloiche 132/33kV: 200 MW waiting
- Bhlaraidh 132/33kV: 101 MW waiting