Cloiche 132/33kV: grid connection queue
Cloiche 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Feb 2028 to 1 Feb 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cloiche Wind Farm | SSE GENERATION LIMITED | Onshore wind | 200 | 1 Feb 2028 | High | 31 Mar 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Wester Drummond Primary | SSEN Distribution | 0.5 km | 0 MW | 0.1 MW |
| Ardochy Primary | SSEN Distribution | 1.3 km | 0 MW | 0.1 MW |
| Foyers Primary | SSEN Distribution | 8.1 km | 0 MW | 0 MW |
| Glendoe Primary | SSEN Distribution | 8.2 km | 0 MW | 0.7 MW |
| Bunoich Primary | SSEN Distribution | 10.0 km | 0 MW | 1.8 MW |
| Fort Augustus GSP | SSEN Distribution | 12.4 km |
Thinking of connecting near Cloiche 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Loch Kemp 275kV Switching Station: 660 MW waiting
- Bhlaraidh 132/33kV: 101 MW waiting
- Dell 132kV: 50 MW waiting
- Fort Augustus 400kV: 200 MW waiting
- Fort Augustus 2 400kV: 115 MW waiting