Dell 132kV: grid connection queue

Dell 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Apr 2030 to 1 Apr 2030.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
50 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Dell Wind FarmDELL WIND FARM LIMITEDOnshore wind501 Apr 2030High16 Feb 2032Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Ardochy PrimarySSEN Distribution6.4 km0 MW0.1 MW
Wester Drummond PrimarySSEN Distribution7.1 km0 MW0.1 MW
Glendoe PrimarySSEN Distribution10.0 km0 MW0.7 MW
Bunoich PrimarySSEN Distribution12.6 km0 MW1.8 MW
Fort Augustus GSPSSEN Distribution14.3 km
Foyers PrimarySSEN Distribution14.5 km0 MW0 MW

Thinking of connecting near Dell 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points