Corriegarth 132/33kV substation: grid connection queue

Corriegarth 132/33kV substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 70 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Jul 2027 to 31 Jul 2027.

1project in the queue
70 MWwaiting to connect
69 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
70 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Corriegarth 2 Wind FarmCORRIEGARTH 2 WIND FARM LIMITEDOnshore wind7031 Jul 2027High27 Sep 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Errogie PrimarySSEN Distribution9.3 km0 MW0 MW
Ardochy PrimarySSEN Distribution9.8 km0 MW0.1 MW
Wester Drummond PrimarySSEN Distribution10.6 km0 MW0.1 MW
Foyers PrimarySSEN Distribution10.8 km0 MW0 MW
Drumnadrochit PrimarySSEN Distribution17.8 km0 MW2 MW
Glendoe PrimarySSEN Distribution18.0 km0 MW0.7 MW

Thinking of connecting near Corriegarth 132/33kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points