Aberarder Wind Farm 132/33kV: grid connection queue
Aberarder Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Aug 2026 to 31 Aug 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Aberarder Wind Farm | ABERARDER WIND FARM LLP | Onshore wind | 50 | 31 Aug 2026 | n/a | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Errogie Primary | SSEN Distribution | 8.4 km | 0 MW | 0 MW |
| Inverarnie Primary | SSEN Distribution | 14.8 km | 0 MW | 0 MW |
| Foyers Primary | SSEN Distribution | 15.1 km | 0 MW | 0 MW |
| Tomatin Primary | SSEN Distribution | 16.9 km | 0 MW | 0 MW |
| Drumnadrochit Primary | SSEN Distribution | 17.2 km | 0 MW | 2 MW |
| Ardochy Primary | SSEN Distribution | 18.9 km | 0 MW | 0.1 MW |
Thinking of connecting near Aberarder Wind Farm 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Aberarder Extension Wind Farm 132/33kV: 138 MW waiting
- Corriegarth 132/33kV substation: 70 MW waiting
- INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION: 45 MW waiting
- FARR WIND FARM 132/33KV SUBSTATION: 145 MW waiting
- Loch na Cathrach 275kV Switching Station: 550 MW waiting