FARR WIND FARM 132/33KV SUBSTATION: grid connection queue

FARR WIND FARM 132/33KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 145 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Jan 2030 to 30 Jan 2030.

1project in the queue
145 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
145 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Farr WindFarmFARR WINDFARM LIMITEDOnshore wind14530 Jan 2030High17 Dec 2031Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Tomatin PrimarySSEN Distribution5.7 km0 MW0 MW
Inverarnie PrimarySSEN Distribution7.6 km0 MW0 MW
Hilton PrimarySSEN Distribution15.5 km0 MW0 MW
Inverness PrimarySSEN Distribution15.9 km0 MW0 MW
Inverness GSPSSEN Distribution15.9 km
Raigmore PrimarySSEN Distribution16.5 km0 MW0 MW

Thinking of connecting near FARR WIND FARM 132/33KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points