Loch Kemp 275kV Switching Station: grid connection queue

Loch Kemp 275kV Switching Station · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 660 MW is waiting to connect here (largest by capacity: hydro, pumped storage and tidal). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.

1project in the queue
660 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Loch Kemp PSHLOCH KEMP STORAGE LIMITEDHydro, pumped storage and tidal66031 Oct 2030Medium31 Oct 2030Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Wester Drummond PrimarySSEN Distribution3.5 km0 MW0.1 MW
Ardochy PrimarySSEN Distribution4.1 km0 MW0.1 MW
Foyers PrimarySSEN Distribution5.6 km0 MW0 MW
Glendoe PrimarySSEN Distribution10.0 km0 MW0.7 MW
Bunoich PrimarySSEN Distribution11.2 km0 MW1.8 MW
Errogie PrimarySSEN Distribution12.0 km0 MW0 MW

Thinking of connecting near Loch Kemp 275kV Switching Station?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.