Bhlaraidh 132/33kV: grid connection queue

Bhlaraidh 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 101 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 17 Aug 2029 to 17 Aug 2029.

1project in the queue
101 MWwaiting to connect
108 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
101 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bhlaraidh Extension Wind FarmSSE GENERATION LIMITEDOnshore wind10117 Aug 2029High4 Jul 2031Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Wester Drummond PrimarySSEN Distribution5.0 km0 MW0.1 MW
Ardochy PrimarySSEN Distribution5.8 km0 MW0.1 MW
Foyers PrimarySSEN Distribution6.7 km0 MW0 MW
Glendoe PrimarySSEN Distribution9.3 km0 MW0.7 MW
Bunoich PrimarySSEN Distribution10.0 km0 MW1.8 MW
Fort Augustus GSPSSEN Distribution12.3 km

Thinking of connecting near Bhlaraidh 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points