Loch Nan Eun 275/18kV: grid connection queue
Loch Nan Eun 275/18kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 900 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fort Augustus Storage | GLENDOE STORAGE LIMITED | Battery storage | 900 | 31 Oct 2029 | Medium | 31 Oct 2029 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Fort Augustus Storage | 1 May 2031 | 31 Oct 2029 | -18 months |
| 13 Oct 2026 | Fort Augustus Storage | 31 Oct 2029 | 1 May 2031 | +18 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Fort Augustus GSP | SSEN Distribution | 1.3 km | ||
| Bunoich Primary | SSEN Distribution | 1.8 km | 0 MW | 1.8 MW |
| Glendoe Primary | SSEN Distribution | 3.3 km | 0 MW | 0.7 MW |
| Aberchalder Primary | SSEN Distribution | 5.4 km | 0 MW | 0.1 MW |
| Invergarry Primary | SSEN Distribution | 10.0 km | 0 MW | 0.9 MW |
| Wester Drummond Primary | SSEN Distribution | 11.2 km | 0 MW | 0.1 MW |
Thinking of connecting near Loch Nan Eun 275/18kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Fort Augustus 400kV: 200 MW waiting
- Fort Augustus 2 400kV: 115 MW waiting
- FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION: 50 MW waiting
- Tomchrasky Wind Farm 132/33kV: 63 MW waiting
- Cloiche 132/33kV: 200 MW waiting