Tomchrasky Wind Farm 132/33kV: grid connection queue
Tomchrasky Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 63 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Mar 2032 to 31 Mar 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tomchrasky Wind Farm | E Power Limited | Onshore wind | 63 | 31 Mar 2032 | Low | 31 Mar 2032 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 10 Nov 2026 | Tomchrasky Wind Farm | 31 Oct 2029 | 31 Mar 2032 | +29 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ceannacroc GSP | SSEN Distribution | 6.9 km | ||
| Fort Augustus GSP | SSEN Distribution | 7.9 km | ||
| Bunoich Primary | SSEN Distribution | 9.1 km | 0 MW | 1.8 MW |
| Aberchalder Primary | SSEN Distribution | 10.3 km | 0 MW | 0.1 MW |
| Glendoe Primary | SSEN Distribution | 11.6 km | 0 MW | 0.7 MW |
| Invergarry Primary | SSEN Distribution | 11.7 km | 0 MW | 0.9 MW |
Thinking of connecting near Tomchrasky Wind Farm 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Loch Nan Eun 275/18kV: 900 MW waiting
- Fort Augustus 400kV: 200 MW waiting
- Fort Augustus 2 400kV: 115 MW waiting
- FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION: 50 MW waiting
- Beinneun Windfarm 2: 144 MW waiting