Jonhstone 132/33kV: grid connection queue
Jonhstone 132/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 60 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 28 Jun 2028 to 28 Jun 2028.
1project in the queue
60 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
60 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Scottish Water Linwood STW 60MW BESS | Bluestone Linwood 1 Ltd | Battery storage | 60 | 28 Jun 2028 | High | 28 Jun 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Jonhstone 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.