Artfield Forest Wind Farm 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 86 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 28 Jun 2030 to 28 Jun 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Artfield Forest Wind Farm | ARTFIELD FOREST WIND FARM LTD | Onshore wind | 86 | 28 Jun 2030 | High | 14 May 2032 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Glenluce | SP Energy Networks | 10.3 km | 8 MW | 5.3 MW |
| Newton Stewart | SP Energy Networks | 17.2 km | 26 MW | 3.6 MW |
| Stranraer | SP Energy Networks | 18.7 km | 27 MW | 1.9 MW |
Thinking of connecting near Artfield Forest Wind Farm 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Stranoch Wind 132/33kV: 102 MW waiting
- Arecleoch 132/33kV: 289 MW waiting
- Glenvernoch 132kV: 96 MW waiting
- Chirmorie Wind Farm substation: 91 MW waiting
- Newton Stewart: 73 MW waiting