Stranoch Wind 132/33kV: grid connection queue
Stranoch Wind 132/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 102 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 18 Dec 2026 to 18 Dec 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stranoch Wind Farm | STRANOCH WINDFARM LIMITED | Onshore wind | 102 | 18 Dec 2026 | High | 14 Feb 2029 | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 25 Aug 2026 | Stranoch Wind Farm | 9 Oct 2026 | 18 Dec 2026 | +2 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Stranraer | SP Energy Networks | 13.9 km | 27 MW | 1.9 MW |
| Glenluce | SP Energy Networks | 14.0 km | 8 MW | 5.3 MW |
| Auchneel | SP Energy Networks | 15.3 km | 25 MW | 3.2 MW |
| Pinwherry | SP Energy Networks | 17.4 km | 7 MW | 5.4 MW |
Thinking of connecting near Stranoch Wind 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Mid Moile Wind Farm 275/132kV Substatio: 99 MW waiting
- Artfield Forest Wind Farm 132kV: 86 MW waiting
- Arecleoch 132/33kV: 289 MW waiting
- Chirmorie Wind Farm substation: 91 MW waiting
- Ladyburn 132kV: 206 MW waiting