Ladyburn 132kV: grid connection queue
Ladyburn 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 206 MW are waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 29 Aug 2031 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Craig Nab Wind Energy Hub | Craig Nab Wind Energy Hub Limited | Onshore wind + storage | 36 | 29 Aug 2031 | High | 15 Jul 2033 | Scoping | 1 |
| Craiglarie Wind Farm | Invenergy Development UK Ltd | Onshore wind + storage | 170 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Stranraer | SP Energy Networks | 1.1 km | 27 MW | 1.9 MW |
| Auchneel | SP Energy Networks | 2.8 km | 25 MW | 3.2 MW |
| Glenluce | SP Energy Networks | 14.3 km | 8 MW | 5.3 MW |
| Barrhill | SP Energy Networks | 17.0 km | 7.9 MW | 8.5 MW |
Thinking of connecting near Ladyburn 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Mid Moile Wind Farm 275/132kV Substatio: 99 MW waiting
- Stranoch Wind 132/33kV: 102 MW waiting
- Artfield Forest Wind Farm 132kV: 86 MW waiting
- Arecleoch 132/33kV: 289 MW waiting
- Chirmorie Wind Farm substation: 91 MW waiting