Benzene

Arecleoch 132/33kV: grid connection queue

Arecleoch 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 289 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Aug 2026 to 15 Jun 2032.

2projects in the queue
289 MWwaiting to connect
114 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Arecleoch Extension WindfarmScottishPower Renewables (UK) LimitedOnshore wind7331 Aug 2026n/aScopingnone
ArecleochScottishPower Renewables (UK) LimitedOnshore wind21615 Jun 2032Low15 Jun 2032Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
PinwherrySP Energy Networks9.5 km7 MW5.4 MW

Thinking of connecting near Arecleoch 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points