Glenvernoch 132kV: grid connection queue
Glenvernoch 132kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 96 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glenvernoch | ENERGYFARM UK GLENVERNOCH LTD | Onshore wind + storage | 96 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Newton Stewart | SP Energy Networks | 10.7 km | 26 MW | 3.6 MW |
| Creetown | SP Energy Networks | 18.8 km | 7.8 MW | 8.7 MW |
Thinking of connecting near Glenvernoch 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- BLAIR HILL WIND FARM 132KV SUBSTATION: 99 MW waiting
- Newton Stewart: 73 MW waiting
- Artfield Forest Wind Farm 132kV: 86 MW waiting
- Chirmorie Wind Farm substation: 91 MW waiting
- Arecleoch 132/33kV: 289 MW waiting