Benzene

BLAIR HILL WIND FARM 132KV SUBSTATION: grid connection queue

BLAIR HILL WIND FARM 132KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 99 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.

1project in the queue
99 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Blair Hill Wind FarmRenewable Energy Systems LimitedOnshore wind9931 Oct 2036Low31 Oct 2036Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Newton StewartSP Energy Networks7.2 km26 MW3.6 MW
CreetownSP Energy Networks14.0 km7.8 MW8.7 MW

Thinking of connecting near BLAIR HILL WIND FARM 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points