Benzene

Chirmorie Wind Farm substation: grid connection queue

Chirmorie Wind Farm substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 91 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Apr 2027 to 30 Apr 2027.

1project in the queue
91 MWwaiting to connect
0 MWalready connected
91 MWholding Gate 2
0date moves since 2 Jun 2026
91 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Chirmorie Wind FarmCHIRMORIE WIND FARM LIMITEDOnshore wind9130 Apr 2027High27 Jun 2029Consents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
PinwherrySP Energy Networks8.5 km7 MW5.4 MW

Thinking of connecting near Chirmorie Wind Farm substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points