South Anglia Connection Node B 400kV: grid connection queue
South Anglia Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,420 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Great Oak Solar | RWE Renewables UK Solar and Storage Limited | Solar + storage | 700 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Butlers Energy Project | IG RENEWABLES SPV 1 LTD | Solar + storage | 480 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
| Butlers Wood PV & BESS Station | IB VOGT UK LTD | Solar + storage | 240 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Halstead Primary 11kV | UK Power Networks | 3.1 km | 16 MW | 0.7 MW |
| Lake & Elliot Primary 11kV | UK Power Networks | 6.3 km | 13 MW | 3.1 MW |
| Braintree Depot Primary 11kV | UK Power Networks | 7.1 km | 21 MW | 12 MW |
| Wethersfield Primary 11kV | UK Power Networks | 8.4 km | 12 MW | 4.9 MW |
| Coggeshall Primary 11kV | UK Power Networks | 9.4 km | 14 MW | 6.1 MW |
| West Braintree Primary 11kV | UK Power Networks | 9.4 km | 22 MW | 9.1 MW |
Thinking of connecting near South Anglia Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Braintree 400kV: 1,107 MW waiting
- South Anglia Connection Node C 400kV: 4,874 MW waiting
- South Anglia Connection Node A 400kV: 1,240 MW waiting
- South Anglia Connection Node D 132kV: 400 MW waiting
- Pelham 400kV: 480 MW waiting