Braintree 400kV: grid connection queue
Braintree 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,107 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2026 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Braintree (Tertiary) | CSE22 LIMITED | Solar + storage | 50 | 30 Oct 2026 | n/a | Consents Approved | none | |
| Braintree | PIVOTED POWER LLP | Solar + storage | 57 | 30 May 2027 | High | 29 May 2029 | Consents Approved | 2 |
| Braintree | Braintree 10 Renewables Limited | Solar + storage | 1,000 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | Braintree | 30 Oct 2024 | 30 May 2027 | +31 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lake & Elliot Primary 11kV | UK Power Networks | 1.0 km | 13 MW | 3.1 MW |
| Braintree Depot Primary 11kV | UK Power Networks | 1.1 km | 21 MW | 12 MW |
| West Braintree Primary 11kV | UK Power Networks | 2.9 km | 22 MW | 9.1 MW |
| Braintree Local 33kV | UK Power Networks | 2.9 km | 92 MW | 28 MW |
| Witham Primary 11kV | UK Power Networks | 8.5 km | 20 MW | 17 MW |
| Coggeshall Primary 11kV | UK Power Networks | 8.5 km | 14 MW | 6.1 MW |
Thinking of connecting near Braintree 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- South Anglia Connection Node C 400kV: 4,874 MW waiting
- South Anglia Connection Node B 400kV: 1,420 MW waiting
- South Anglia Connection Node D 400kV: 1,000 MW waiting
- Bulls Lodge 400kV: 1,000 MW waiting
- South Anglia Connection Node A 400kV: 1,240 MW waiting