South Anglia Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 4,874 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 31 Oct 2032 to 31 Oct 2036.

5projects in the queue
4,874 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Rat Hall Mod AppKingsway Solar Farm LimitedSolar + storage70031 Oct 2032Low31 Oct 2032Scoping1
Lacey's Farm BESSBluestone Energy LtdBattery storage92431 Oct 2033Low31 Oct 2033Scoping1
CorytonCoryton 10 Renewables LimitedSolar1,00031 Oct 2034Low31 Oct 2034Scoping1
NatPower Tilbury Green Energy ParkNATPOWER MARINE UK LIMITEDBattery storage1,00031 Oct 2034Low31 Oct 2034Scoping1
Cold NortonBSR APPLICATIONS LIMITEDMixed and other1,25031 Oct 2036Low31 Oct 2036Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
West Braintree Primary 11kVUK Power Networks1.0 km22 MW9.1 MW
Braintree Local 33kVUK Power Networks1.0 km92 MW28 MW
Lake & Elliot Primary 11kVUK Power Networks3.5 km13 MW3.1 MW
Braintree Depot Primary 11kVUK Power Networks4.1 km21 MW12 MW
Dunmow Primary 11kVUK Power Networks10.1 km22 MW9 MW
Witham Primary 11kVUK Power Networks10.7 km20 MW17 MW

Thinking of connecting near South Anglia Connection Node C 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points