Pelham 400kV: grid connection queue

Pelham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 480 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 May 2035 to 31 May 2035.

1project in the queue
480 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Pelham GEC (Ethos Green)PELHAM GREEN ENERGY CENTRE LTDBattery storage48031 May 2035Low31 May 2035Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Thaxted Grid 33kVUK Power Networks5.1 km44 MW50 MW
Thaxted Local 11kVUK Power Networks5.1 km1.1 MW-3.1 MW
Wethersfield Primary 11kVUK Power Networks6.6 km12 MW4.9 MW
Haverhill Primary 11kVUK Power Networks8.9 km12 MW4.2 MW
Acrows Primary 11kVUK Power Networks11.0 km3.1 MW15 MW
Saffron Walden Primary 11kVUK Power Networks11.3 km23 MW2.3 MW

Thinking of connecting near Pelham 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.