PELHAM 2 400KV SUBSTATION: grid connection queue
PELHAM 2 400KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Pelham BESS | PELHAM ENERGY PARK LIMITED | Battery storage | 250 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Thaxted Grid 33kV | UK Power Networks | 5.1 km | 44 MW | 50 MW |
| Thaxted Local 11kV | UK Power Networks | 5.1 km | 1.1 MW | -3.1 MW |
| Wethersfield Primary 11kV | UK Power Networks | 6.6 km | 12 MW | 4.9 MW |
| Haverhill Primary 11kV | UK Power Networks | 8.9 km | 12 MW | 4.2 MW |
| Acrows Primary 11kV | UK Power Networks | 11.0 km | 3.1 MW | 15 MW |
| Saffron Walden Primary 11kV | UK Power Networks | 11.3 km | 23 MW | 2.3 MW |
Thinking of connecting near PELHAM 2 400KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pelham 400kV: 480 MW waiting
- South Anglia Connection Node B 400kV: 1,420 MW waiting
- South Anglia Connection Node C 400kV: 4,874 MW waiting
- Braintree 400kV: 1,107 MW waiting
- South Anglia Connection Node D 132kV: 400 MW waiting