Bishopbriggs BESS 400/275kV: grid connection queue
Bishopbriggs BESS 400/275kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 28 May 2029 to 28 May 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bishopbriggs 500MW BESS | GPC Project 16 Ltd | Battery storage | 500 | 28 May 2029 | Medium | 28 May 2029 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Bishopbriggs | SP Energy Networks | 0.4 km | 23 MW | 8.4 MW |
| Milton | SP Energy Networks | 2.3 km | 18 MW | 14 MW |
| Petershill Road | SP Energy Networks | 3.1 km | 24 MW | 11 MW |
| Flemington Street | SP Energy Networks | 3.1 km | 22 MW | 12 MW |
| Denmark Street | SP Energy Networks | 3.3 km | 11 MW | |
| Balmore | SP Energy Networks | 3.5 km | 14 MW |
Thinking of connecting near Bishopbriggs BESS 400/275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Whitehill Bess 275/132kV: 500 MW waiting
- Finnieston: 60 MW waiting
- Elvanfoot 275/132/33kV: 250 MW waiting
- Easterhouse 275kV: 200 MW waiting
- Killermont: 43 MW waiting