Kirkcaldy BESS 132kV: grid connection queue

Kirkcaldy BESS 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.

1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kirkcaldy BESSApatura Battery LtdBattery storage10031 Oct 2032Low31 Oct 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
RedhouseSP Energy Networks0.4 km10 MW10 MW
ChapelSP Energy Networks2.6 km12 MW3.4 MW
Birrell Street WyndSP Energy Networks2.8 km24 MW8.3 MW
Linton LaneSP Energy Networks3.6 km8.3 MW4.4 MW
Cluny RoadSP Energy Networks3.8 km6.6 MW
PitteucharSP Energy Networks4.1 km12 MW

Thinking of connecting near Kirkcaldy BESS 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.