Creyke Beck 400kV: grid connection queue

Creyke Beck 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

6 projects with 7,578 MW are waiting to connect here (largest by capacity: gas and thermal, offshore wind). Contracted dates run from 30 Jun 2028 to 31 Oct 2039.

6projects in the queue
7,578 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
2,628 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Creyke Beck Battery 2CBB SPV LIMITEDBattery storage2830 Jun 2028High30 Jun 2030Consents Approvednone
Hornsea Power Station 4ORSTED HORNSEA PROJECT FOUR LIMITEDOffshore wind2,60030 Oct 2028High14 Nov 2030Scopingnone
CREYKE BECKCLEAN AIR RENEWABLES LIMITEDSolar + storage50031 May 2033Low31 May 2033Scopingnone
Creyke Beck PV & BESS SubBEFERLEAH ENERGY PARK LIMITEDSolar + storage25030 May 2035Low30 May 2035Scoping1
Bute Hydrogen Project 2HALDANE ENERGY PROJECT 2 LIMITEDGas and thermal3,60030 Oct 2035Low30 Oct 2035Scoping1
Flinton RoadFLINTON ROAD SOLAR LIMITEDSolar + storage60031 Oct 2039Low31 Oct 2039Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Creyke Beck 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points