North Humber Connection Node A 400kV: grid connection queue
North Humber Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,000 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Chapel Rush Solar | RWE Renewables UK Solar and Storage Limited | Solar + storage | 600 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| GF Thornton Energy BESS | THORNTON ENERGY LTD | Battery storage | 400 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | GF Thornton Energy BESS | 31 Oct 2033 | 30 Oct 2035 | +24 months |
Thinking of connecting near North Humber Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Birkhill Wood 400kV: 4,350 MW waiting
- North Humber Connection Node B 132kV: 200 MW waiting
- North Humber Connection Node C 132kV: 40 MW waiting
- North Humber Connection Node E 400kV: 1,680 MW waiting
- Creyke Beck 400kV: 7,578 MW waiting