North Humber Connection Node A 400kV: grid connection queue

North Humber Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,000 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.

2projects in the queue
1,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Chapel Rush SolarRWE Renewables UK Solar and Storage LimitedSolar + storage60030 Oct 2035Low30 Oct 2035Scoping1
GF Thornton Energy BESSTHORNTON ENERGY LTDBattery storage40030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026GF Thornton Energy BESS31 Oct 203330 Oct 2035+24 months

Thinking of connecting near North Humber Connection Node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points