Birkhill Wood 400kV: grid connection queue
Birkhill Wood 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 4,350 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 30 Oct 2030 to 31 Oct 2031.
3projects in the queue
4,350 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Dogger Bank South East | RWE Renewables UK Dogger Bank South (East) Limited | Offshore wind | 1,450 | 30 Oct 2030 | Medium | 30 Oct 2030 | Scoping | none |
| Dogger Bank South West | RWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMITED | Offshore wind | 1,450 | 30 Oct 2030 | Medium | 30 Oct 2030 | Scoping | none |
| Dogger Bank D Offshore Wind Farm | Doggerbank Offshore Wind Farm Project 4 Projco Limited | Offshore wind | 1,450 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Birkhill Wood 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Humber Connection Node A 400kV: 1,000 MW waiting
- North Humber Connection Node B 132kV: 200 MW waiting
- North Humber Connection Node C 132kV: 40 MW waiting
- Osbaldwick (North Humber Connection Node E) 132kv: 200 MW waiting
- North Humber Connection Node E 400kV: 1,680 MW waiting