North Humber Connection Node E 400kV: grid connection queue

North Humber Connection Node E 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

3 projects with 1,680 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2033 to 30 Oct 2035.

3projects in the queue
1,680 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Natpower Upsall Green Energy ParkBELLMOOR ENERGY PARK LIMITEDBattery storage1,00031 Oct 2033Low31 Oct 2033Scoping1
OVERTON440MW BESSCARE POWER (OVERTON) LIMITEDBattery storage44030 Oct 2035Low30 Oct 2035Scopingnone
Lightsource OvertonLightsource Renewable UK Development LimitedSolar + storage24030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near North Humber Connection Node E 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points