Creyke Beck: grid connection queue

Creyke Beck GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 470 MW are waiting to connect here (largest by capacity: solar). Contracted dates run from 31 May 2033 to 30 Oct 2039.

2projects in the queue
470 MWwaiting to connect
100 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Creyke Beck Solar FarmRWE Renewables UK Solar and Storage LimitedSolar32031 May 2033Low31 May 2033Scopingnone
KENLEY HOUSE SOLAR PARKBOOM DEVELOPMENTS LTDSolar15030 Oct 2039Low30 Oct 2039Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Creyke Beck?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.