Linnmill: grid connection queue
Linnmill GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 20 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Aug 2032 to 30 Aug 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Brae WF | WIND 2 LIMITED | Onshore wind + storage | 20 | 30 Aug 2032 | Low | 30 Aug 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Symington | SP Energy Networks | 7.1 km | 12 MW | 3.3 MW |
| Corra Linn | SP Energy Networks | 9.3 km | 4.6 MW | 8 MW |
| Lanark | SP Energy Networks | 10.4 km | 26 MW | 17 MW |
| Douglas West | SP Energy Networks | 10.4 km | 22 MW | 15 MW |
| Lesmahagow | SP Energy Networks | 12.6 km | 10 MW | 15 MW |
| Biggar | SP Energy Networks | 12.7 km | 12 MW | 2.7 MW |
Thinking of connecting near Linnmill?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- M74 West Wind Farm 132kV: 180 MW waiting
- Redshaw 132kV Substation.: 620 MW waiting
- Redshaw 400kV: 504 MW waiting
- Bodinglee Wind Farm 132kV: 280 MW waiting
- REDSHAW 132kV B BOARD SUBSTATION: 108 MW waiting