REDSHAW 132kV B BOARD SUBSTATION: grid connection queue
REDSHAW 132kV B BOARD SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 108 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Grayside Wind Farm | GRAYSIDE WF LTD | Onshore wind | 108 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Symington | SP Energy Networks | 7.7 km | 12 MW | 3.3 MW |
| Biggar | SP Energy Networks | 10.2 km | 12 MW | 2.7 MW |
| Corra Linn | SP Energy Networks | 17.6 km | 4.6 MW | 8 MW |
| Douglas West | SP Energy Networks | 18.0 km | 22 MW | 15 MW |
| Lanark | SP Energy Networks | 18.2 km | 26 MW | 17 MW |
Thinking of connecting near REDSHAW 132kV B BOARD SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Linnmill: 20 MW waiting
- Whitelaw Brae 'A' and 'B' 33kV Substations: 57 MW waiting
- Whitelaw Brae BESS 33kV substation: 1 MW waiting
- Redshaw Energy Park 132kV substation: 500 MW waiting
- Blacklaw 132/33kV: 222 MW waiting