Whitelaw Brae 'A' and 'B' 33kV Substations: grid connection queue
Whitelaw Brae 'A' and 'B' 33kV Substations · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 57 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Jul 2026 to 31 Jul 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Whitelaw Brae Windfarm | WHITELAW BRAE WINDFARM LIMITED | Onshore wind | 57 | 31 Jul 2026 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Symington | SP Energy Networks | 16.1 km | 12 MW | 3.3 MW |
| Biggar | SP Energy Networks | 16.2 km | 12 MW | 2.7 MW |
| Moffat | SP Energy Networks | 17.8 km | 8.5 MW | 3.6 MW |
Thinking of connecting near Whitelaw Brae 'A' and 'B' 33kV Substations?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Whitelaw Brae BESS 33kV substation: 1 MW waiting
- Blacklaw 132/33kV: 222 MW waiting
- REDSHAW 132kV B BOARD SUBSTATION: 108 MW waiting
- ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION: 75 MW waiting
- Elvanfoot substation: 44 MW waiting