Farmoor 400kV: grid connection queue

Farmoor 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 840 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
840 MWwaiting to connect
0 MWalready connected
840 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Botley West - Cote Solar Power StationSOLARFIVE LTDSolar84031 Oct 2031Medium31 Oct 2031Awaiting Consents2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Botley West - Cote Solar Power Station30 Oct 202631 Oct 2031+60 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Eynsham PrimarySSEN Distribution4.4 km0 MW0 MW
North Hinksey PrimarySSEN Distribution4.6 km0 MW0 MW
Oxford (Osney) BSPSSEN Distribution5.6 km0 MW0 MW
Oxford PrimarySSEN Distribution5.7 km0 MW0 MW
Frenchay Road PrimarySSEN Distribution6.2 km0 MW0 MW
Yarnton BSPSSEN Distribution6.8 km0 MW0 MW

Thinking of connecting near Farmoor 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.