Cowley 400kV: grid connection queue
Cowley 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,157 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 14 Nov 2025 to 30 Nov 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cowley (Tertiary) | COWLEY BALDON GREEN LIMITED | Solar + storage | 57 | 14 Nov 2025 | n/a | Scoping | none | |
| Cowley Energy Storage | BW ESS DEVELOPMENT UK LIMITED | Battery storage | 200 | 14 Jul 2028 | High | 14 Jul 2030 | Consents Approved | 2 |
| Cowley Farm | COWLEY 2 RENEWABLES LTD | Solar + storage | 200 | 1 Oct 2038 | Low | 1 Oct 2038 | Scoping | 1 |
| Cowley Farm 2 | COWLEY 7 RENEWABLES LTD | Solar + storage | 700 | 30 Nov 2038 | Low | 30 Nov 2038 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Cowley Farm 2 | 1 Oct 2038 | 30 Nov 2038 | +2 months |
| 13 Oct 2026 | Cowley Farm 2 | 30 Nov 2038 | 1 Oct 2038 | -2 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| North Hinksey Primary | SSEN Distribution | 1.1 km | 0 MW | 0 MW |
| Oxford (Osney) BSP | SSEN Distribution | 1.3 km | 0 MW | 0 MW |
| Oxford Primary | SSEN Distribution | 1.4 km | 0 MW | 0 MW |
| St Ebbes Primary | SSEN Distribution | 2.4 km | 0 MW | 0 MW |
| University Parks Primary | SSEN Distribution | 3.1 km | 0 MW | 0 MW |
| Frenchay Road Primary | SSEN Distribution | 3.2 km | 0 MW | 0 MW |
Thinking of connecting near Cowley 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Botley West 400kV: 1,280 MW waiting
- Botley 400kV: 800 MW waiting
- Farmoor 400kV: 840 MW waiting
- Culham Jet 400kV: 500 MW waiting
- Appleford 400kV: 1,000 MW waiting