Culham Jet 400kV: grid connection queue
Culham Jet 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Culham Storage | CULHAM STORAGE LIMITED | Battery storage | 500 | 31 Oct 2029 | Medium | 31 Oct 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 11 Aug 2026 | Culham Storage | 29 Oct 2027 | 31 Oct 2029 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Culham Primary | SSEN Distribution | 1.5 km | 0 MW | 16 MW |
| Winsmore Lane Primary | SSEN Distribution | 2.6 km | 0 MW | 0 MW |
| Wootton Road Primary | SSEN Distribution | 3.6 km | 0 MW | 0 MW |
| Milton Primary | SSEN Distribution | 3.8 km | 0 MW | 0 MW |
| Kennington Primary | SSEN Distribution | 5.7 km | 0 MW | 1.2 MW |
| Drayton BSP | SSEN Distribution | 5.7 km | 0 MW | 0 MW |
Thinking of connecting near Culham Jet 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Appleford 400kV: 1,000 MW waiting
- APPLEFORD 400kV SUBSTATION: 900 MW waiting
- Didcot 400kV: 600 MW waiting
- Didcot 132kV: 150 MW waiting
- DIDCOT 400/132KV SUBSTATION: 100 MW waiting