Didcot 400kV: grid connection queue
Didcot 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 600 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2027 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Didcot Energy Park | BROCKWELL STORAGE & SOLAR LIMITED | Battery storage | 300 | 31 Oct 2027 | High | 30 Oct 2029 | Awaiting Consents | none |
| Didcot Road | DIDCOT BESS LIMITED | Battery storage | 300 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Didcot Road | 31 Oct 2027 | 31 Oct 2028 | +12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Milton Primary | SSEN Distribution | 1.1 km | 0 MW | 0 MW |
| Fulscot Primary | SSEN Distribution | 4.1 km | 0 MW | 0 MW |
| Drayton BSP | SSEN Distribution | 4.5 km | 0 MW | 0 MW |
| Culham Primary | SSEN Distribution | 4.7 km | 0 MW | 16 MW |
| Winsmore Lane Primary | SSEN Distribution | 5.3 km | 0 MW | 0 MW |
| Harwell Primary | SSEN Distribution | 6.2 km | 0 MW | 39 MW |
Thinking of connecting near Didcot 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Didcot 132kV: 150 MW waiting
- DIDCOT 400/132KV SUBSTATION: 100 MW waiting
- Didcot 132kV GIS: 100 MW waiting
- Appleford 400kV: 1,000 MW waiting
- APPLEFORD 400kV SUBSTATION: 900 MW waiting