Didcot 132kV: grid connection queue
Didcot 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sutton Courtenay | RWE Generation UK Plc | Battery storage | 150 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Milton Primary | SSEN Distribution | 1.1 km | 0 MW | 0 MW |
| Fulscot Primary | SSEN Distribution | 4.1 km | 0 MW | 0 MW |
| Drayton BSP | SSEN Distribution | 4.5 km | 0 MW | 0 MW |
| Culham Primary | SSEN Distribution | 4.7 km | 0 MW | 16 MW |
| Winsmore Lane Primary | SSEN Distribution | 5.3 km | 0 MW | 0 MW |
| Harwell Primary | SSEN Distribution | 6.2 km | 0 MW | 39 MW |
Thinking of connecting near Didcot 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Didcot 400kV: 600 MW waiting
- DIDCOT 400/132KV SUBSTATION: 100 MW waiting
- Didcot 132kV GIS: 100 MW waiting
- Appleford 400kV: 1,000 MW waiting
- APPLEFORD 400kV SUBSTATION: 900 MW waiting