Botley West 400kV: grid connection queue
Botley West 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,280 MW are waiting to connect here (largest by capacity: mixed and other, solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Buckland Marsh Solar Park | Arise Renewable Energy UK Limited | Solar + storage | 280 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
| West Botley High Impact Green Energy Hub | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Eynsham Primary | SSEN Distribution | 4.3 km | 0 MW | 0 MW |
| North Hinksey Primary | SSEN Distribution | 4.5 km | 0 MW | 0 MW |
| Oxford (Osney) BSP | SSEN Distribution | 5.2 km | 0 MW | 0 MW |
| Oxford Primary | SSEN Distribution | 5.3 km | 0 MW | 0 MW |
| Frenchay Road Primary | SSEN Distribution | 5.6 km | 0 MW | 0 MW |
| Yarnton BSP | SSEN Distribution | 6.1 km | 0 MW | 0 MW |
Thinking of connecting near Botley West 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Botley 400kV: 800 MW waiting
- Farmoor 400kV: 840 MW waiting
- Cowley 400kV: 1,157 MW waiting
- Culham Jet 400kV: 500 MW waiting
- Appleford 400kV: 1,000 MW waiting