Bolney 400kV: grid connection queue
Bolney 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,504 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 29 May 2028 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bolney (tertiary) | BOLNEY GREEN LIMITED | Solar + storage | 57 | 29 May 2028 | High | 29 May 2030 | Scoping | 1 |
| Rampion Extension Offshore Wind Farm | RAMPION EXTENSION DEVELOPMENT LIMITED | Offshore wind | 1,200 | 31 Dec 2029 | Medium | 31 Dec 2029 | Scoping | none |
| Bolney | PIVOTED POWER LLP | Solar + storage | 48 | 31 Jan 2031 | Medium | 31 Jan 2031 | Scoping | none |
| Bolney Farm | Dragon Green 2 Renewables Ltd | Solar + storage | 200 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 8 Sep 2026 | Rampion Extension Offshore Wind Farm | 1 Aug 2026 | 31 Dec 2029 | +41 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cowfold 11kV | UK Power Networks | 3.7 km | 14 MW | 2.3 MW |
| Southwater 11kV | UK Power Networks | 5.2 km | 19 MW | 15 MW |
| Bolney Grid 33kV | UK Power Networks | 5.3 km | 25 MW | 12 MW |
| Horsham Grid 11kV | UK Power Networks | 6.3 km | 73 MW | 31 MW |
| Goddards Green Grid 33kV | UK Power Networks | 9.7 km | 114 MW | 38 MW |
| Goddards Green 11kV | UK Power Networks | 9.7 km | 18 MW | 12 MW |
Thinking of connecting near Bolney 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bolney 132kV: 250 MW waiting
- Bolney: 50 MW waiting
- DRAGON GREEN 400kV SUBSTATION: 750 MW waiting
- Little Horsted: 50 MW waiting
- West Weybridge 275kV: 57 MW waiting