Little Horsted: grid connection queue

Little Horsted GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Little HorstedCSE34 LIMITEDSolar + storage5031 Oct 2031Medium31 Oct 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Uckfield 11kVUK Power Networks3.3 km22 MW9.4 MW
Buxted 11kVUK Power Networks5.8 km8.2 MW3.2 MW
Lewes Grid 33kVUK Power Networks7.0 km82 MW44 MW
Newick 11kVUK Power Networks8.1 km7.9 MW5.6 MW
Lewes Town 11kVUK Power Networks8.3 km20 MW2.4 MW
Ripe 11kVUK Power Networks8.8 km1.9 MW-3.3 MW

Thinking of connecting near Little Horsted?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.