Little Horsted: grid connection queue
Little Horsted GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Little Horsted | CSE34 LIMITED | Solar + storage | 50 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Uckfield 11kV | UK Power Networks | 3.3 km | 22 MW | 9.4 MW |
| Buxted 11kV | UK Power Networks | 5.8 km | 8.2 MW | 3.2 MW |
| Lewes Grid 33kV | UK Power Networks | 7.0 km | 82 MW | 44 MW |
| Newick 11kV | UK Power Networks | 8.1 km | 7.9 MW | 5.6 MW |
| Lewes Town 11kV | UK Power Networks | 8.3 km | 20 MW | 2.4 MW |
| Ripe 11kV | UK Power Networks | 8.8 km | 1.9 MW | -3.3 MW |
Thinking of connecting near Little Horsted?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Ninfield 400kV: 1,050 MW waiting
- Ninfield: 370 MW waiting
- Sussex and Romney Connection Node A 400kV: 4,042 MW waiting
- DRAGON GREEN 400kV SUBSTATION: 750 MW waiting
- Bolney 400kV: 1,504 MW waiting