Sussex and Romney Connection Node A 400kV: grid connection queue
Sussex and Romney Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
11 projects with 4,042 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Little Horsted | Lightsource Renewable UK Development Limited | Solar + storage | 57 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Little Horsted Energy Park | ELEMENTS GREEN DEVELOPMENT LTD | Solar + storage | 1,260 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
| Ninfield | Ninfield 10 Renewables Limited | Solar + storage | 1,000 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| STABLE GREEN ENERGY | LH NGET GRID SERVICES LIMITED | Battery storage | 500 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
| Zenobe Little Horsted BESS | ZENOBE ENERGY LIMITED | Battery storage | 300 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| Ninfield BESS | Kona Energy Limited | Battery storage | 225 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| New Little Horsted 200MW Solar and BESS | PRIVATE ENERGY PARTNERS (UK) LTD | Solar + storage | 200 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| TH Ninfield | FRV Powertek Limited | Battery storage | 200 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| KXP Alpha 1 Little Horsted | KXP ALPHA I LIMITED | Battery storage | 100 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| KXP Alpha 2 Little Horsted | KXP ALPHA II LIMITED | Battery storage | 100 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| KXP Alpha 3 Little Horsted | KXP ALPHA III LIMITED | Battery storage | 100 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Ninfield | 31 Oct 2030 | 31 Oct 2037 | +84 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ninfield Grid 33kV | UK Power Networks | 6.3 km | 102 MW | 36 MW |
| Ninfield Local 11kV | UK Power Networks | 6.3 km | 5.3 MW | 1.5 MW |
| Mountfield 11kV | UK Power Networks | 6.8 km | 14 MW | 1.9 MW |
| Broad Oak 11kV | UK Power Networks | 8.2 km | 8.1 MW | 6 MW |
| Horam 11kV | UK Power Networks | 8.4 km | 12 MW | 2 MW |
| Horsebridge 11kV | UK Power Networks | 10.0 km | 14 MW | 3.4 MW |
Thinking of connecting near Sussex and Romney Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Ninfield 400kV: 1,050 MW waiting
- Ninfield: 370 MW waiting
- Sussex and Romney Connection Node B 400kV: 1,440 MW waiting
- Sussex and Romney Connection Node B 132kV: 225 MW waiting
- Little Horsted: 50 MW waiting