Ninfield: grid connection queue
Ninfield GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 370 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 6 Dec 2036 to 9 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Saver & Pashley Farm Energy Park | ELGIN ENERGY ES CO LIMITED | Solar + storage | 130 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
| Catsfield | MAS 001 Limited | Battery storage | 240 | 9 Nov 2037 | Low | 9 Nov 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Broad Oak 11kV | UK Power Networks | 4.3 km | 8.1 MW | 6 MW |
| Mountfield 11kV | UK Power Networks | 7.6 km | 14 MW | 1.9 MW |
| Horam 11kV | UK Power Networks | 8.0 km | 12 MW | 2 MW |
| Robertsbridge 11kV | UK Power Networks | 9.2 km | 13 MW | 9 MW |
| Ticehurst 11kV | UK Power Networks | 10.2 km | 9 MW | 8.6 MW |
| Ninfield Grid 33kV | UK Power Networks | 10.3 km | 102 MW | 36 MW |
Thinking of connecting near Ninfield?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Ninfield 400kV: 1,050 MW waiting
- Sussex and Romney Connection Node A 400kV: 4,042 MW waiting
- Sussex and Romney Connection Node B 400kV: 1,440 MW waiting
- Little Horsted: 50 MW waiting
- Sussex and Romney Connection Node B 132kV: 225 MW waiting