Benzene

Sussex and Romney Connection Node B 132kV: grid connection queue

Sussex and Romney Connection Node B 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 225 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
225 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lanehurst Farm BESSELGIN ENERGY ES CO LIMITEDBattery storage22531 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Little Common 11kVUK Power Networks5.3 km22 MW9.6 MW
Bexhill Town 11kVUK Power Networks5.8 km23 MW5.2 MW
Pevensey Bay 11kVUK Power Networks7.9 km14 MW7.1 MW
Ninfield Local 11kVUK Power Networks10.0 km5.3 MW1.5 MW
Ninfield Grid 33kVUK Power Networks10.0 km102 MW36 MW
Eastbourne Grid 33kVUK Power Networks10.7 km58 MW22 MW

Thinking of connecting near Sussex and Romney Connection Node B 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points