Benzene

Bolney 132kV: grid connection queue

Bolney 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 250 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
250 MWwaiting to connect
36 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hookers Farm BESSAncleggan LimitedBattery storage25031 Oct 2031Medium31 Oct 2031Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cowfold 11kVUK Power Networks3.7 km14 MW2.3 MW
Southwater 11kVUK Power Networks5.2 km19 MW15 MW
Bolney Grid 33kVUK Power Networks5.3 km25 MW12 MW
Horsham Grid 11kVUK Power Networks6.3 km73 MW31 MW
Goddards Green Grid 33kVUK Power Networks9.7 km114 MW38 MW
Goddards Green 11kVUK Power Networks9.7 km18 MW12 MW

Thinking of connecting near Bolney 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.