Lyndhurst: grid connection queue

Lyndhurst GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
50 MWholding Gate 2
0date moves since 2 Jun 2026
50 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Templeton BESSTempleton Battery Storage LimitedBattery storage5031 Oct 2028High31 Oct 2030Consents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
MacAlpine Road PrimarySSEN Distribution0.1 km0 MW0 MW
West Kirkton PrimarySSEN Distribution1.2 km0 MW0 MW
Lyndhurst GSPSSEN Distribution1.4 km
Lyndhurst PrimarySSEN Distribution1.4 km0 MW0 MW
Lochee PrimarySSEN Distribution2.4 km0 MW0 MW
Charleston GSPSSEN Distribution3.0 km

Thinking of connecting near Lyndhurst?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points