Tealing 400kV: grid connection queue
Tealing 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 1,900 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tealing Energy Park | ONPATH ENERGY LIMITED | Battery storage | 1,400 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| Akku Tealing Battery Storage | Akku Tealing Limited | Battery storage | 500 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Longhaugh Primary | SSEN Distribution | 4.8 km | 0 MW | 7.5 MW |
| West Kirkton Primary | SSEN Distribution | 4.9 km | 0 MW | 0 MW |
| Leoch Primary | SSEN Distribution | 5.5 km | 0 MW | 4 MW |
| MacAlpine Road Primary | SSEN Distribution | 5.6 km | 0 MW | 0 MW |
| Old Craigie Road Primary | SSEN Distribution | 6.3 km | 0 MW | 6.9 MW |
| Milton of Craigie GSP | SSEN Distribution | 6.8 km |
Thinking of connecting near Tealing 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Tealing 132kV: 700 MW waiting
- Tealing IDNO 132/33kV: 80 MW waiting
- Lyndhurst: 50 MW waiting
- Milton of Craigie: 68 MW waiting
- Charleston GSP 132/33kV: 70 MW waiting