Benzene

Milton of Craigie: grid connection queue

Milton of Craigie GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 68 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

2projects in the queue
68 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Pitkerro RoadVital Energi Solutions LimitedBattery storage5031 Oct 2033Low31 Oct 2033Scopingnone
Barns of Wedderburn (ABEI ENERGY GREEN VI)ABEI ENERGY LIMITEDSolar + storage1831 Oct 2033Low31 Oct 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Ashludie PrimarySSEN Distribution3.6 km0 MW0 MW
Edzell Street PrimarySSEN Distribution3.8 km0 MW7.5 MW
Baldovie PrimarySSEN Distribution3.8 km0 MW7.5 MW
Longhaugh PrimarySSEN Distribution4.1 km0 MW7.5 MW
Broughty Ferry PrimarySSEN Distribution5.0 km0 MW5.5 MW
Milton of Craigie GSPSSEN Distribution5.1 km

Thinking of connecting near Milton of Craigie?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points