Charleston GSP 132/33kV: grid connection queue
Charleston GSP 132/33kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 70 MW are waiting to connect here (largest by capacity: battery storage, solar). Contracted dates run from 30 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stoneygroves PV | Enviromena Project Management UK Limited | Solar | 20 | 30 Oct 2031 | Medium | 30 Oct 2031 | Scoping | 1 |
| Lyndhurst Camperdown BESS | Geocore Ltd | Battery storage | 50 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Gourdie Primary | SSEN Distribution | 1.7 km | 0 MW | 2.2 MW |
| Ninewells Primary | SSEN Distribution | 2.4 km | 0 MW | 7.6 MW |
| Charleston GSP | SSEN Distribution | 2.7 km | ||
| Charleston Primary | SSEN Distribution | 2.7 km | 0 MW | 4 MW |
| Menzieshill Primary | SSEN Distribution | 3.0 km | 0 MW | 10 MW |
| Lyndhurst GSP | SSEN Distribution | 4.5 km |
Thinking of connecting near Charleston GSP 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Lyndhurst: 50 MW waiting
- Tealing 400kV: 1,900 MW waiting
- Tealing 132kV: 700 MW waiting
- Tealing IDNO 132/33kV: 80 MW waiting
- Milton of Craigie: 68 MW waiting